Guide · Production planning

Your average multiplication rate will make you late

Your average multiplication rate will make you late

Almost every tissue culture lab I know plans deliveries the same way. Take the line's average multiplication rate, compound it forward, and read off the week you will have enough plantlets. It looks like arithmetic, so nobody questions it. It is also wrong in a direction that makes you late far more often than it makes you early.

Two times four is not three times three

Take a line that averages a 3× multiplication rate. One culture today, three after the next subculture, nine after the one after that. Now take a second line with the same 3× average that gets there unevenly: a slow cycle where it only doubles, then a good cycle where it quadruples.

STARTAFTER CYCLE 1AFTER CYCLE 2Steadyaverage 3××3×39Unevenaverage 3××2×48
Both lines average 3× per cycle. The steady one ends with nine cultures. The uneven one ends with eight.
3 × 3 = 9Steady, average 3×
2 × 4 = 8Uneven, average 3×

Same average, one plantlet in nine missing, after only two cycles. Nothing was lost to contamination and nobody made a mistake. Growth multiplies, and an average only tells the truth about things that add.

Any unevenness costs something, and the cost grows with the size of the swing:

Two cyclesAverage rateCultures from one
3.0× then 3.0×3×9.00
2.8× then 3.2×3×8.96
2.5× then 3.5×3×8.75
2.0× then 4.0×3×8.00

“But the good cycles make up for the bad ones”

This is the natural objection, and it is half right. Suppose each cycle is a coin flip between 2× and 4×. Over two cycles there are four equally likely results.

below the planat or above the plan
2× then 2×42× then 4×84× then 2×84× then 4×16plan from the average: 9cultures after two cycles, starting from 1
The four results average exactly 9, so the plan is right on average. Three of the four still come in short.

Add them up and the average result is 9, exactly what the plan said. But the average is held up by the one run that quadrupled twice. You do not get to deliver the average of four possible futures. You get one of them, and three times out of four it is a short one.

That is the whole problem. Compounding the average rate tells you the average outcome. A delivery date needs the likely outcome, and with multiplication the likely outcome sits below the average.

Real rates follow a bell curve

No real line flips between exactly 2× and 4×. A real line's rate wanders around its average from one cycle to the next: a tired medium batch, a slow week in the growth room, a different technician, a little more loss than usual. Plot those cycle rates and you get something close to a bell curve.

average 3×about 19 cycles in 202×2.5×3×3.5×4×MULTIPLICATION RATE IN ONE CYCLE
An illustrative line: 3× on average, with nearly every cycle landing between 2× and 4×. The curve is symmetric, so a single cycle is as likely to beat 3× as to miss it.

For one cycle, the average is a fair bet. Half the time you beat it. The trouble starts when you chain cycles together, because a delivery is rarely one cycle away.

Ten cycles out

Say a customer wants plantlets ten cycles from now. One culture compounding at 3× for ten cycles is 59,049, so that is what the spreadsheet promises. Here is what happens if you run that same line, with that same bell curve, a few hundred thousand times.

below the planat or above the plan
the plan: 59,04959% fall short41% reach it030k59k118k177kMIDDLE RUN: ABOUT 52,000CULTURES AFTER TEN CYCLES
Each cycle's rate was drawn from the bell curve above. The symmetric curve going in becomes a lopsided one coming out: most runs pile up below the plan, and a thin tail of lucky runs stretches far past it.
41%
Of runs reach the 59,049 the average promised. The middle run finishes with about 52,000, and one run in five finishes with about 32,500 or fewer, barely half the plan.

The average of all those runs is still 59,049. The plan is not biased. It is just describing a number that most individual runs never see, because a handful of runs that finish with well over a hundred thousand pull the average up.

The farther the date, the worse the odds

Every extra cycle between today and the delivery gives the unevenness one more chance to compound, so the odds slide the farther out you promise.

0%25%50%12345678910111250%44%41%CYCLES BETWEEN TODAY AND THE DELIVERY
Chance of having what the average-rate plan says you will have, by how many cycles away the delivery is. Same illustrative line as above.

How many cycles behind?

“Short on plantlets” and “late” are the same thing seen from two sides. If the line is at half the plan on the delivery date, it is a fraction of a cycle from catching up, and you can measure the shortfall in cycles. Here is the ten-cycle delivery again, counted that way.

on time or aheadbehind
on schedule41% on time or ahead59% behind1 ahead½ ahead0½ behind1 behind1½ behindCYCLES AHEAD OF OR BEHIND THE PLAN ON THE DELIVERY DATE
The same runs as the chart above, measured in cycles of growth. Counted this way the lopsided curve becomes a bell again, but its center sits behind the schedule, not on it.
0.5 of a cycle
Is how far behind one run in five is on the delivery date. One run in ten is at least 0.8 of a cycle behind. If a cycle is four weeks, that is two to three weeks late on an order you planned to the day.

The delay grows with the distance to the delivery, and it grows faster for the unlucky runs than for the typical one:

Delivery isMiddle run is behind by1 run in 5 is behind by at least1 run in 10 is behind by at least1 in 5, at four weeks a cycle
2 cycles out0.010.210.32about 1 week
5 cycles out0.050.350.52about 1 week
10 cycles out0.120.540.78about 2 weeks
15 cycles out0.180.700.99about 3 weeks

All figures are in cycles of growth. A line cannot be cut a fraction of a cycle early, so in practice a line that is half a cycle behind ships a full cycle late, or ships short. On this line, waiting one extra cycle gets you the planned number 94% of the time. That gap is the “we are running a little behind” call, and it was in the numbers on the day the order was taken.

Try it on your own numbers

Set your line's average rate, how much it moves from cycle to cycle, and how many cycles away the delivery is. The model reruns the line 20,000 times in your browser.

Your line, rerun 20,000 times
of runs reach the average-rate plan
of the plan is what the middle run delivers
is the rate to plan with to be right 8 times in 10
is how far behind 1 run in 5 is on the delivery date
below the planat or above the plan

Which variation counts

There is a fair objection here too. One jar gives five shoots and its neighbor gives none. Surely that averages out across a few thousand jars?

It does. Jar-to-jar differences inside one large lot mostly cancel, and for a big established line they are not what hurts you. Two kinds of variation do not cancel:

  1. Anything the whole lot shares in a cycle. One medium batch, one growth room, one season, one crew that week. If the whole lot does 2.6× this cycle, there is no other half of the lot doing 3.4× to balance it.
  2. Small numbers. A new line coming up from twenty cultures has no crowd to average over. Early cycles of a ramp are exactly where the rate swings most, and they are multiplied by every cycle that follows.

So the lines most exposed are the ones you are most likely to be making promises about: new introductions, and anything with a long ramp to a first delivery.

What I do about it: plan to a certainty

The fix is not a bigger fudge factor. It is deciding how sure you want to be, and letting the line's own numbers tell you what that costs.

  1. Average the right way. To get the rate a line really compounded at, divide what you ended with by what you started with and take the root for the number of cycles. A line that went 2× then 4× grew at 2.83× per cycle, not 3×. Adding the rates and dividing always flatters you.
  2. Measure the swing, not only the average. Keep the rate of every cycle for every line. The spread of those numbers is what tells you how far to trust a date.
  3. Choose a certainty, not a rate. Decide how often you are willing to miss: one order in five, one in ten. That is a business decision, and it is the only number here that is yours to pick. The rate to plan with follows from it.
  4. Simulate the line to find that rate. This is what a Monte Carlo simulation is for, and it is what the model above does. Run the line thousands of times with its measured swing, sort the results, and read off the one you beat as often as you chose. On the line above, 80% certainty means planning at 2.83× and promising about 32,500 plantlets from each starting culture. 90% means 2.75× and about 25,200. The average promised 59,049.
  5. Hold more margin for far dates than near ones. A delivery two cycles out needs very little. One ten cycles out needs a lot. A flat “add ten percent” is too much for the first and nowhere near enough for the second.
  6. Re-plan from the count every week. Each cycle that finishes replaces a guess with a fact. A plan that is redone from this week's real inventory catches a slow line while there is still time to cut more or call the customer.

Certainty is not free. Planning at 90% means carrying more cultures and doing more cutting than planning at 80%, and most weeks some of that turns out to be surplus. What you are buying is fewer late orders. The point is to make that trade on purpose.

How InVitroManager plans this way

Doing this by hand for every line, every week, is not realistic. It is the part of the job I built the planner to do.

  1. You set the certainty. Each plan has a certainty setting, a percent. It is the answer to “how often should this plan hold?”
  2. The rates and their swing come from your own records. Every time a technician records a subculture at the hood, the planner learns a little more about that line's rate and how much it moves.
  3. Each step is planned at the rate that certainty calls for. Not the average. The margin grows with the number of subcultures between the cultures on the shelf today and the delivery, so a far order is planned more cautiously than a near one.
  4. It separates the two kinds of variation. Swings a whole lot shares in a week are treated differently from jar-to-jar differences, because only the shared part compounds.
  5. It re-plans from the current count. A line running ahead has its work trimmed. A line running behind shows up while there is still time to act.
  6. It tells you when a date cannot be met at your certainty. The plan does not quietly assume the average to make the numbers work. It marks the delivery, and you decide whether to cut more, move the date, or call the customer.
If you plan your delivery dates with your average multiplication rate, you will be behind more often than you are on time, and further behind the farther out the date is.

So here is my question for anyone quoting delivery dates from a lab. When you compound a rate forward, which rate are you using: the one your line averages, or the one it actually beats most of the time?